EPC Improvement Plan

The PAS 2035 medium-term improvement plan, explained for homeowners

If a funded retrofit scheme or a whole-house retrofit is in your future, you may be handed a medium-term improvement plan written under PAS 2035. It is the formal version of an EPC improvement plan. This page explains what PAS 2035 is, who writes the plan, what it must contain and how to read one, so you can check it does its job.

Been given a plan and not sure what it means? Send the main points with your EPC details and we reply by email.

Send your EPC details Use the plan builder

What PAS 2035 is

PAS 2035 is a specification and guidance document for retrofitting existing homes to improve their energy efficiency, published by the British Standards Institution. The current edition, PAS 2035:2023, is the second edition, published in September 2023. It is used together with PAS 2030:2023, which covers the installation of the measures themselves. The earlier PAS 2035:2019 edition, with its 2022 amendment, was withdrawn on 30 March 2025. BSI reviews the document at intervals of no more than two years.

Its purpose is to make retrofit work safer and more effective by putting a whole-house view in front of individual measures, and its 2023 revision put more emphasis on protecting the consumer. In practice that means an assessment of the house, an evaluation of the options, a plan, a design, installation, and checks afterwards, each with a named role responsible.

The roles you may meet

RoleWhat they do in the process
Retrofit AssessorAssesses the dwelling: its construction, condition, energy use and the people who live there
Retrofit CoordinatorManages the project, evaluates the improvement options and is responsible for the medium-term improvement plan
Retrofit DesignerDesigns and specifies the measures agreed from the plan
Installer or Main ContractorInstalls the measures to PAS 2030
Retrofit EvaluatorCarries out further monitoring and evaluation where it is required

On a small project one firm may fill several roles. What matters is that each role's work is done and recorded.

What a medium-term improvement plan is for

PAS 2035 describes the plan's purpose as guiding the staged improvement of a home: identifying the improvements needed, setting an appropriate order for them, and highlighting the critical interactions between them. It also expects the plan to be updated as standards and technologies change and as each improvement is made. The 2023 edition turned the contents of the plan from guidance into a requirement and requires a plan for every dwelling in a project, even where only limited work can be afforded in the short term. The point is to see the whole route before spending on the first step.

The Retrofit Coordinator prepares it, working with the Retrofit Designer and with you as the client. Before the plan, the coordinator carries out an improvement options evaluation using the assessment's RdSAP, SAP or PHPP data. That evaluation works out the simple payback of each candidate measure on its own (its capital cost divided by the estimated yearly fuel saving) and its carbon cost-effectiveness, then does the same for the proposed package. The standard asks for capital costs specific to your home, not generic per-house prices.

The six things the plan must do

Paraphrasing clause 8.1.7 of PAS 2035:2023, the plan must:

  1. Identify the constraints that come from the building's history, construction, character and setting, and from how it is used.
  2. Identify the set of measures, including enabling works, needed to reach an appropriate improvement target without harming comfort, health and safety or the building's integrity.
  3. Identify interactions between measures, so a whole-house approach is followed and problems such as thermal bridging are avoided.
  4. Set the order in which the measures are to be installed, bearing in mind that some are best done together and some can make later ones harder.
  5. Include a monitoring and evaluation plan, at minimum a basic check at the end of each stage.
  6. Be presented so it can be updated as work proceeds and as new knowledge, products and technologies arrive.

The coordinator then reviews the options, the recommended package and the plan with you and agrees the scope, the intended outcomes, the energy performance target and the budget.

The order the standard favours

PAS 2035 sets out "fabric first" as the approach that should always be considered when a retrofit plan is put together. In outline: bring the fabric into good repair, do the low-cost measures, improve insulation and airtightness while keeping ventilation adequate, meet the remaining heat demand efficiently, and only then add low and zero carbon technologies such as solar. It allows for sensible exceptions, such as replacing a worn-out boiler before the insulation can be afforded, and for a risk-based approach on older, traditional or protected buildings where some insulation options are unsuitable or irreversible.

When you are likely to be given one

You will meet PAS 2035 mostly through funded schemes. For ECO4, Ofgem says the measures for a home are set by a retrofit assessment and that installers must be TrustMark registered. A council or installer delivering a funded scheme may therefore send a retrofit assessor before any work is agreed, and the plan that follows will drive what is installed. You can also commission a retrofit assessment and coordinator privately for a self-funded whole-house project.

How to read the plan you are given

How this site's plan relates to a PAS 2035 plan

The plan builder and template on this site follow the same structure and order, so a plan you make here will make sense to a retrofit coordinator later. It is not a PAS 2035 plan: we are an information site, not retrofit assessors or coordinators, and we do not visit homes. Use our plan to understand your options and prepare; use a PAS 2035 plan when a funded or whole-house project requires one.

Send us your EPC details and we will reply by email

Tell us what your EPC says and what you want to reach. We read every message and reply by email.

We reply by email. This is an independent information site: we do not pass your details to installers or assessors, and we do not book surveys or visits. See our privacy notice.

Questions people ask

What is a medium-term improvement plan?

The plan, required by PAS 2035 for every dwelling in a retrofit project, that sets out the measures a home needs, their order, their interactions and how each stage will be checked. The Retrofit Coordinator is responsible for it.

Is PAS 2035 a legal requirement?

PAS 2035 is a BSI standard, not legislation. It becomes a requirement where a scheme or contract requires it, which is common for government-funded retrofit.

Which edition applies now?

PAS 2035:2023, the second edition, published in September 2023. The 2019 edition and its 2022 amendment were withdrawn on 30 March 2025.

Does a medium-term improvement plan cover a set number of years?

The standard does not fix a term. It describes the plan as guiding staged improvement over a period of time and expects it to be updated as work is done.

Sources and last checked

Every rule, date and figure on this page comes from the sources below. Where something is a proposal and not yet law, the page says so.

Last checked 25 October 2026. Corrections are welcome through the contact form.